January 24th - Signed Contract
March 16th - Pre-Construction Meeting
Week 1:
March 30th - Broke Ground
Week 2:
April 4th - Beginning of the Foundation
Week 3:
April 14th - Lumber Delivered
April 15th - Basement and Garage Concrete Poured
Week 4:
April 18th - Framing Begins
Week 5:
April 24th - Framing Completed and Windows Installed
Week 6
May 3rd - Plumbing Completed
May 4th - Electrical Started
Week 7:
May 9th - Pre-Drywall Meeting
May 10th - Insulation Complete
May 12th - Passed Energy Star Inspection
Week 8:
May 15th - Drywall Begins
May 17th - Siding Begins
May 19th - Siding and Drywall Completed
Week 9:
May 24th - Trim, Columns and Cabinets,
Concrete for front porch and steps and back porch and steps
Week 10:
May 27th - We have electricity!
May 31st - Granite
June 3rd - Bathroom Tile Installed
Week 11:
June 6th - Flooring Installation Begins
Week 12:
June 12th - Front Porch Railings and Latice completed
June 13th - Appliances Delivered; Sinks, Faucets & Toilets Installed
Week 13:
June 19th - Sod and Landscaping Completed
Week 14:
June 28th - Final walk through
June 30th - Settlement